Why are people so uncomfortable making a decision? I admit I scratch my head frequently at some
of the issues that land on my plate because someone was uncomfortable making a
decision – or because they feel they haven’t accumulated enough information.
This is not a phenomenon unique to my current
organization. I’ve seen it across most organizations
that I’ve worked in. Managers have
engrained into people that they are not allowed to make decisions and that they
must review everything prior to anything getting done. YIKES!
And then we wonder why people fail!
Better yet, we wonder why people leave us and move on to a new job –
leaving us to spread the workload around to others on the team.
Look, I won’t claim my teams are exempt from this
pattern. But I do try to encourage
people to think through problems they are facing and if they are unsure of a
direction, at least bring options into the conversation when we sit down to
have a discussion. This at least allows
me to see that they have thought through the problem and are attempting to
address the issue. Usually through
conversation they’ll come to some type of a conclusion, thank me for the
discussion and head back out.
I think where we struggle the most within my current teams is
getting people to make estimates on project activity. This is a personal decision by team members
measuring how much work they will be responsible for against requested project
activity. When we first introduced this
concept, there was a lot of push-back.
And to be frank, there were a lot of errors in the initial estimates. But over time, people have grown more
confident and are estimates are aligning better with the actuals that we
measure over the life of a given project.
We go through regular training with people that are new on
our teams. It really doesn’t matter if
they’ve been in development or whether they are new to the ropes. Most developers have never been trained on
how to produce reliable estimates.
So how do you pull together an estimate – well, for one
thing, it’s different depending on what stage of the project you’re in:
- Discovery Phase: Usually estimates
at this stage are done by someone within the management chain along with senior
level technology resources. How? Well, the truth of the matter is the project
scope is looked at in comparison to other projects that have been completed
that smell like or look like they have similar impacts.
- Requirements Phase: Typically this
is a minor refinement of the estimate that was given in the Discovery
Phase. Any changes to scope are
accounted for and typically there are additional details highlighted that point
to previously unconsidered impacts.
- Technical Design Phase: Now we are
putting some meat on the bone. At this
point, technical resources have engaged and identified impacts across current
systems/application silos and have also identified where new functionality must
be created. Along with the technical
estimates business teams have assessed impacts to current and new
processes. Between the two paths, the
full project estimate is considerably more accurate than anything that was put
together in the first 2 phases of the lifecycle.
- Development Phase: Some
organizations perform the final detail design in this phase. If so, this is the last chance to update
those estimates both from a technical and business perspective. This should allow the resources that are
going to do the actual work to review the technical designs, identify the
specific chunks of code or the business processes that are going to change the
final say in what amount of time is necessary to complete project activity.
Rules of the road when it comes to performing estimates:
- If you’re implementing new technology
into your current technology stack – maybe you also need to set aside time to install
and integrate the technology.
- Don’t forget process changes. Sometimes these changes can be just as
critical to the project timeline as the technology changes. Don’t underestimate the impacts these can
have across your teams.
- Don’t forget testing – and I’m not
just talking about QA. I’m talking about
Unit Testing, Integration Testing, Parallel Testing, Performance Testing, Regression Testing, New Feature/Function
Testing, and UAT Testing.
- Don’t forget implementation
planning and actual implementation activity.
While the universe may have been created with a big bang – in most
instances you are going to see implementation activity spread out over a period
of time. Some implementation activity
begins before the code touches production, and some activity happens months
after the code is in production – you need to account for all of the activity.
- Don’t forget to provide a buffer
for 3rd party activity. I
have yet to see a 3rd party engagement go off without some type of
change that has to happen. The initial
timeline provided for the engagement never usually is achieved.
Items for consideration when building the estimates:
- How many screen modifications need
to be made?
- How many new screens are there in
the project?
- How many web services need to be
modified?
- How many new web services are
there in the project?
- How many reports/data extracts
need to be modified?
- How many new reports/data extracts
need to be created.
- How many tables/stored procedures
need to be modified?
- How many new tables/stored
procedures need to be created?
- How many 3rd party apps
need to be touched?
- How many new 3rd party
integration activities are needed?
- How many processes need to be
modified?
- How many new processes need to be
created?
- What infrastructure changes are
needed – servers, server types, routers, switches, security devices?
- What new infrastructure pieces
need to be installed – servers, routers, switches, security devices?
Realize that you’re first efforts are going to be wildly off
base. Don’t be afraid to tell your team
that you’re giving them time to get better at creating estimates. This means when they’re wrong – it’s a
conversation not a point against them in their annual review. Use each estimate as a coaching opportunity
when the final numbers come in – what they did right and what didn’t look so
good and how do we make it better.
This by no means covers it all, but points you
in the right direction. Now I’ve heard
some people say that in an Agile process you don’t need to worry about
this. Yeah, right. Trust me, someone in the organization is
telling the CFO what this thing your building is going to cost – how many 2
week iterations it’s going to take to get full functionality. If you’re not responsible for making those
conversations happen today – you will be at some point. Better to start figuring this out know,
before you’re asked to provide that first estimate.
Realize that you’re first efforts are going to be wildly off
base. Don’t be afraid to tell your team
that you’re giving them time to get better at creating estimates. This means when they’re wrong – it’s a
conversation not a point against them in their annual review. Use each estimate as a coaching opportunity
when the final numbers come in – what they did right and what didn’t look so
good and how do we make it better.